Minister of rural roads warns contractors behind schedule on PAPR and PAEMePR

Infrastructure
Tuesday, 02 February 2021 16:51
Minister of rural roads warns contractors behind schedule on PAPR and PAEMePR

(Togo First) - The companies in charge of maintenance and construction work under the Rural Road Support Program (PAPR) and the Annual Mechanized Maintenance Program for Rural Roads (PAEMePR) are behind schedule. 

According to the minister of rural roads, Kanfitine Tchede Issa, who called the firms “black sheep,” the two projects concerned should have been completed respectively in 12-14 months and 4-6 months. In effect, however, some of the contractors have consumed 114% of the set schedule, for a completion rate of 65.5% only. 

The minister thus warned the companies to catch up on their delay within two months maximum. Otherwise, they will be issued an ultimatum, and if necessary their contracts will be terminated. 

Séna Akoda