Lomé-Kpalimé road is 15% complete in five months of work

Infrastructure
Wednesday, 18 November 2020 16:08
Lomé-Kpalimé road is 15% complete in five months of work

(Togo First) - Started last June, the Lomé-Kpamé national road (RN5) modernization works are 15% complete, for 14.5% of the set time for completion. The news was disclosed by EBOMAF, the West African construction giant in charge of the project.

“The work has been slowed down greatly, but we are managing, said EBOMAF’s CEO, Mahamadou Bonkoungou. He stressed that he is personally engaged in the project, to ensure that the best quality is delivered. 

The works, which are set to be completed in 36 months, were assessed during a field visit by Prime Minister Victoire Tomegah Dogbé. On this occasion, she said the works could be completed before the deadline, looking at the progress made and the technical equipment mobilized.

35985 ebomaf tat davancement des travaux red

In effect, the undergoing project aims at reinforcing and rehabilitating the 120 km-long roads for CFA195 billion (excluding tax). In addition to this amount, there is CFA19 billion to rehabilitate roads and utilities in Kpalimé. 

Around 3,000 young Togolese are working on the project. 